Subject: Execution of Construction & Installation Operations 
Project location: Tehran
Area: 38,000 m2
Beneficiary: The Court of Administrative Justice
Client: Tehran Municipality, Development Organization
Designer: Gueno Consultant Engineers
Supervisor: Gueno Consultant Engineers

 

Golhak Negin Commercial/Office Building

Subject: Construction & facility installation operations
Project location: Tehran
Infrastructure: 18,000 (m2)
Beneficiary: Different administrative & commercial departments
Client: Iranian - e - atlas investment company
Designer: Arcolog consultant engineers
Supervisor: Arcolog consultant engineers

Construction of Office & Industrial Building

Subject: Construction of General Buildings plus Electrical & Mechanical Operations of Office & Industrial Buildings
Project location:Tehran
Area: 41,000 m2
Client: ** Government Funded Projects
Designer: ** Government Funded Projects
Supervisor: ** Government Funded Projects
Contract amount: $31.932 Million  [(Price List of 2015) (Reference index fourth quarter of the year 2014)] +  25% increasing $39.916 Million
Initiation date: October 22, 2016

Noavar Office Tower

Subject: All structures operation (steel structure with composite roof), construction installation facilities and landscaping.
Project location: Tehran
Infrastructure: 33,000 (m2)
Beneficiary: MCI center
Client: Noavar co. (affiliated to the 15th khordad foundation)
Designer: Bavand consultant engineers
Supervisor: Bavand consultant engineers

Valiasr Vanak Office

Subject: Execution of concrete structure
Project location: Tehran
Infrastructure: 15,000 (m2)
Beneficiary: Ministry of welfare
Client: Iran sazeh co. (affiliated to social security organization)
Designer: Dr. Mirghaderi & the team
Supervisor: Dr. Mirghaderi & the tea
Contract amount: $4.622 Million  (Price List of 2000)
+ 25% increasing $5.778 Million 
Initiation date: November 13, 2000
Temporary hand over: January, 2003
Final invoice & escalation: $1.268 Million 