Subject: Construction & installation operations with landscaping
Project location: Anzali
Area: Total 10,000 (m2)
- Data protection building: 1,150 (m2)
- Headquarters building: 8,560 (m2)
Beneficiary: Nedaja headquarters engineering
Client: Nedaja headquarters engineering
Designer: Gueno consultant engineers
Supervisor: Gueno consultant engineers
Contract amount: $1.505 Million (Price List of 2001)
+ 25% increasing $1.882 Million
Amendment amount $0.214 Million
Initiation date: July 8, 2002
Temporary hand over:
- Headquarters building: December, 2003
- Data protection building: May, 2004
Final invoice & escalation: $2.412 Million
Subject: Excavation & nailing execution
Project location: Tehran
Beneficiary: Oil industries engineering & construction
Client: Oil industries engineering & construction
Designer: Bavand consultant engineers
Supervisor: Bavand consultant engineers
Contract amount: $6.576 Million (Price List of 2003)
Initiation date: August 11, 2003
Temporary hand over: Terminated, due to the lack of construction permit in Aug 2004
Final invoice & escalation: $1.89 Million