Subject: structure, construction & installation operations with landscaping
Project location: Anzali
Area: Total about 2,000 (m2)
- Telecommunication center: 695 (m2)
- Military police building: 1,230 (m2)
- Powerhouse: 240 (m2)
Beneficiary: Nedaja headquarters engineering
Client: Nedaja headquarters engineering
Designer: Gueno consultant engineers
Supervisor: Gueno consultant engineers
Contract amount: $0.574 Million (Price List of 2002)
+ 25% increasing $0.718 Million
Initiation date: February 3, 2003
Temporary hand over:
Telecommunication center & powerhouse: October, 2004
Military police building: August, 2005
Final invoice & escalation: $0.81 Million