Subject: Construction & facility installation operations
Project location: Tehran
Area: 18,000 (m2)
Beneficiary: Different administrative & commercial departments
Client: Iranian - e - atlas investment company
Designer: Arcolog consultant engineers
Supervisor: Arcolog consultant engineers
Contract amount: $4.787 Million (Price List of 2004)
+ 25% increasing $5.959 Million
Initiation date: May 16, 2005
Temporary hand over: February, 2009
Final invoice & escalation: $10.416 Million