Subject: Execution & procurement operation of tabriz tetra pak factory phase1 containing:
-Execution of production hall foundation
-Execution of warehouse foundation
-Construction operation of surrounding walls
-Executive operation of construction and general installations of guard and support buildings.
Project location: Tabriz
Beneficiary: Tetra pak Iran
Client: Tetra pak Iran
Designer: Incotechnic consultant engineers
Supervisor: Incotechnic consultant engineers
Contract amount: $2.386 Million [(Price List of 2009) (Reference index - third quarter of the year 2011)] + 25% increasing $1.909 Million
Initiation date: September 18, 2011
Temporary hand over: January, 2013
Final invoice & escalation: $1.943 Million